| Investigators: Dam collapse not a “force majeure” event The collapse of saddle dam D at the Xe-Pian Xe-Namnoy  hydroelectric power project in Attapeu province last year was not considered as  “force majeure”, a senior government official said yesterday.Vice President of the National  Investigation Committee (NIC) formed by the government to investigate the cause  of the disaster, which killed dozens of villagers and left thousands homeless,  revealed the findings of the investigation at a press conference.
 Mr Singphet Bounsavatthiphanh  said that even if rainfall was quite heavy on the days before the July 23, 2018  failure, the reservoir level was still below the maximum operation level and  well below the crest level when the failure started.
 
 
                        
                          |  |  “Thus, the failure incident  cannot be considered as ‘force majeure’,” he told local media at the Prime  Minister’s Office.The government set up the  National Investigation Committee to thoroughly investigate, verify and report  to the government, the general public, the international community and other  stakeholders with regard to the underlying causes of the collapse of the saddle  dam.
 To ensure the integrity,  reliability, impartiality and transparency of the investigation and the  accurate determination of the causes of the collapse, the Committee engaged and  gave full authority to a panel of professional and independent experts (the  Independent Expert Panel, or IEP) with globally recognised reputations to  conduct an independent investigation and to report the results of that  investigation.
 The IEP‘s members are Professor  Anton J. Schleiss of Switzerland, Honorary President of the International Commission on Large Dams  (ICOLD), Mr Ahmed F. Chraibi of Morocco, former Vice President of ICOLD, and Dr  Jean-Pierre Tournier of Canada, a Vice President of ICOLD.
 ICOLD is widely recognised as  the world's leading professional organisation dedicated to advancing the art  and science of dam engineering.
 In addition, the government  invited foreign parties to take part as observers in the investigation process.
 The government understands that  the Korean company involved in the development of the project is also carrying  out an investigation into the underlying causes of the collapse.
 The investigation conducted by  the IEP was based upon the supporting information available, the IEP's  observations made over the course of three site visits conducted since August  2018, and the results of the recommended post-failure geotechnical  investigations.
 The IEP outlined its findings on  the failure of saddle dam D in a final report, and submitted that report to the  NIC on March 20, 2019, according to Mr Singphet, who is Vice President of the  Government Inspection Authority.
 The IEP found that the failure  could not be considered as “force majeure” as explained above.
 It also found that the root  cause of the failure was related to high permeability combined with erodible  horizons mainly due to the existence of canaliculus interconnected paths. As  the water level rose during the filling of the reservoir, seepage flow  developed in the foundation along these paths and horizons with high  permeability. This resulted in internal erosion and softening of the laterite  soil. When erosion and softening in the foundations reached a certain point,  the dam stability was no longer ensured and a deep rotational sliding at the  highest section of the saddle dam was triggered.
 This finally led to complete  breaching of the saddle dam and its foundations, resulting in the catastrophic  uncontrolled release of water from the reservoir.
 According to the Independent  Expert Panel, the foundation is without doubt involved in the failure, which  could have been prevented by adequate treatment measures.
 
 By Times Reporters(Latest Update May 29, 2019)
 |